West Stroop Sidewalk 2024
Project Update
The contractor is anticipating completing the stone wall by September 5th. They have experienced delays due to material shortage of the stone to complete the wall. The contractor will also be working on the new sidewalk construction working towards the east. The completion of the sidewalk is anticipated in October. During this period, please be aware that one lane of westbound Stroop Road will be closed to facilitate the construction process.
Project Description
Construct a sidewalk on West Stroop
Project Limits
Overland to Southmoor Circle NW
Bid Date: February 1, 2024
Contractor
RB Jergens
Project Engineer: Chad Ingle P.E., P.S.
Email: chad.ingle@ketteringoh.org