Woodman Drive Resurfacing

Project Information

The project includes repair of deteriorated curbs and the repaving of the road.

Status Update

  • September 12: The contractor plans to start milling tomorrow and that will take approximately two days. Then paving will be complete by the end of the next week. Both timelines are weather permitting. There will be lane closures as the contractor completes the work. However, two-way traffic (one lane each direction), access to side streets, and driveways will be maintained at all times.  

Project Location

Woodman Drive from Wilmington Pike to north of Stocker Drive.

Project Engineer

Mike Zink,  PE
Email: Mike.Zink@ketteringoh.org 

Contractor

John R Jurgensen

Bid Tab

Bid Date: March 30, 2023