Wilmington Pike Streetscape Enhancement

Status Update:

August 11, 2017:  Construction to relocate a gas main and telecommunications line on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through mid-August.

Construction of a sidewalk on the west side of Wilmington Pike is progressing north from Stroop Road.  During working hours, one of two southbound lanes will remain open to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

August 4, 2017:  Construction to relocate a gas main and telecommunications line on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through mid-August.  During working hours, one of two southbound travel lanes will remain open to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

Construction of a sidewalk will be in progress next week at the intersection of Wilmington Pike and Stroop Road on the northwest corner and will continue north on Wilmington Pike.  During working hours, one of two southbound (Wilmington Pike) or westbound (Stroop Road) travel lanes will remain open to traffic. Southbound/Westbound drivers may consider an alternate route during peak traffic hours.

July 28, 2017:  Construction to relocate a gas main and telecommunications line on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through mid-August.  During working hours, one of two southbound travel lanes will remain open to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

Construction of sidewalk will be in progress at two locations next week: on Wilmington Pike at Cloverfield Avenue and on Stroop Road, just west of Wilmington Pike.  During working hours, one of two southbound (Wilmington Pike) or westbound (Stroop Road) travel lanes will remain open to traffic. Southbound/Westbound drivers may consider an alternate route during peak traffic hours.

July 21, 2017:  Construction to relocate a gas main and telecommunications line on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through early-August. During working hours, one of two southbound travel lanes will remain open to traffic. Southbound drivers may consider an alternate route during peak traffic hours.

Construction of sidewalk is in progress approximately halfway between Marshall Road and Stroop Road. During working hours, one of two southbound travel lanes will remain open to traffic. Southbound drivers may consider an alternate route during peak traffic hours.

July 13, 2017:  Construction to relocate a gas main and telecommunications line on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through early-August.  During working hours, one of two southbound travel lanes will remain open to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

Construction of sidewalk is in progress approximately halfway between Marshall Road and Stroop Road. During working hours, one of two southbound travel lanes will remain open to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

July 5, 2017:  Construction to relocate a gas main and telecommunications line on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through mid-July.  During working hours, one of two southbound travel lanes will remain open to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

Construction of the sidewalk is scheduled to begin the week of July 3 in the vicinity of Cloverfield Avenue.  During working hours, one of two southbound travel lanes will remain open to traffic.

June 23, 2017:  Construction to relocate a gas main on the west side of Wilmington Pike between Marshall Road and Stroop Road is planned to continue through mid-July.  During working hours, one of two southbound travel lanes will be closed to traffic.  Southbound drivers may consider an alternate route during peak traffic hours.

Construction of the sidewalk and street lights is scheduled to begin in mid-July.

June 12, 2017:  Utility relocations are underway.  Construction is anticipated to begin in the next few weeks.

 

Project Description:  Construction will consist of an eight foot wide concrete shared use path, replacement of street lights and replacement of drive approaches and isolated deteriorated curb.

 

Project Limits:  West side of Wilmington Pike from Marshall Road to Stroop Road, wrapping around on the north side of Stroop Road to the traffic signal at Meijer.

Contractor:

Outdoor Enterprises, LLC                                                                                                                                                                                         8575 Lefevre Road                                                                                                                                                                                         Casstown, OH 45312

 

Bid Results

Bid Tab

 

 

 

Project Engineer:  John Sliemers, P.E.