Wilmington Pike Drainage Improvements

Project Description

This project involves a 24″ storm sewer replacement on Wilmington Pike between Imperial Blvd and Eureka Drive. Additional work shall include the removal and replacement of asphalt pavement.

Project Update:

4/11/2024  This project will begin April 22, 2024 with an estimated completion date of October 19, 2024.

Project Location

Southbound Wilmington Pike between Imperial Blvd and Eureka Drive

Bid Date: February 22, 2024

Bid Results                                           Bid Tab

Contractor

Queen City Mechanicals

Project Engineer: Mike Zink, P.E.
Email: mike.zink@ketteringoh.org