West Stroop Sidewalk Phase 2
Project Description
This project includes the construction of a 5 foot concrete sidewalk, with isolated retaining walls, and curb ramps.
Project Update
Demolition and excavation is near completion and wall construction is expected to start the week of June 2, 2025.
Project Location
Stonebridge Road to Ridgeway Road
Bid Information
Bid Date: February 6, 2025
Contractor: Fillmore Construction
Contact Information
Project Engineer: Mike Zink, P.E.
Email: mike.zink@ketteringoh.org