West Stroop Road – Southern Boulevard to Tait Road-New Sidewalk

Status Update:

November 6, 2019: This project is now complete.

October 17, 2019: The wall is nearing completion with final grading and seeding to follow.

September 26, 2019: The sidewalk construction is complete.

September 18, 2019: The contractor is pouring the sidewalk in front of the wall this week. We are awaiting the delivery of additional stone blocks.

August 27, 2019: The western end of the walk has been completed, top soil added and seeded. Construction of the eastern end of the wall continues.

August 15, 2019: Construction of the stone wall along the sidewalk continues.

August 1, 2019: Sidewalk construction has started on the western part of the project from Tait Road to Moraine Farm’s driveway entrance.

July 29, 2019: Due to rainy conditions, the wall subcontractor is currently working to catch up on other jobs. We hope to have them in town by the end of July.

July 1, 2019: The contractor has completed excavation for the installation of the wall and is working on the necessary base preparation.

June 26, 2019: Preliminary work has begun.

June 18, 2019: Recent rains have delayed the start of this project. Hopefully, it can begin in the next 10 days.

May 28, 2019: This project is scheduled to begin June 3, 2019, weather permitting.

May 1, 2019: A pre-construction meeting will be held this month.

Bid Date: March 21, 2019

Project Description and Limits: A new sidewalk will be constructed to complete the missing link on the north side of West Stroop between Southern Boulevard and Tait Road near Moraine Farm.

Traffic Impacts: Reduction of westbound lane from two lanes to one lane during project.

Bid Results

Bid Tab

Contractor: Double Jay Construction

Project Engineer: John Sliemers, P.E.