West Dorothy Lane Resurfacing

Project Description

The scope of this project along Dorothy Lane includes milling and applying a 2.5-inch asphalt resurfacing over approximately 3.14 miles. The project extends from the intersection with South Dixie Highway to Haig Avenue, just west of the intersection with Wilmington Pike.

Project Update

The final paving on Dorothy Lane is expected to be completed by Friday, July 11, 2025, weather permitting – excluding the intersection at Dixie Highway. Paving at that intersection is scheduled to begin Friday, July 11, 2025 around 8:00 PM and will be done overnight.

Once paving is completed the contractor will begin manhole adjustments, installation of raised pavement markings, traffic loop repairs at the intersection and final pavement striping.

During construction operations, traffic will be reduced to one lane in each direction, and delays are expected.

Project Location

The western terminus of the project is at the corporation limit with the City of Moraine and extends east, stopping just short of Wilmington Pike.

Dorothy Project Map

Bid Information

Bid Date: February 6, 2025

To view bid results and bid tabulations, click on the links below to open the Excel Files.

Bid Results          Bid Tab

Contractor: John R Jurgenson

Contact Information

Project Engineer: Chad Ingle
Email: chad.ingle@ketteringoh.org
Phone: 937-296-2436