Waving Willow Drive – Storm Sewer Improvements & Montgomery County Water Main Replacement

Status Update:

May 31, 2019: The contractor has started replacement on the water main.

May 14, 2019: The contractor is planning to mobilize equipment the week of April 22 and start construction on the water main replacement the third week of May.

April 1, 2019: Work is anticipated to start in May or June.

March 12, 2019: Construction on the project is anticipated to start in May once Vectren has completed the gas main replacement project.

Project Description:The project includes the replacement of the Storm Sewer and Water Mains on Waving Willow. If you have any questions or concerns, please call Ed Schlaack of Montgomery County Environmental Services at 781-2632 or the Kettering Engineering Department at 296-2436.

County Bid Date: January16, 2019

Project Limits: On Waving Willow Drive off of West Schantz Avenue.

Map of Construction Project area

Contractor: CG Construction

Project Engineer: Chad Ingle, P.E.
Email: Chad.ingle@ketteringoh.org