Traffic Signal Replacements Phase 3

Bid Date: February 17, 2022

Status Update

May 17, 2023: Work continues at all locations.

Project Description and Limits

The rebuild will include the installation of new poles, equipment, traffic surveillance cameras, street lights and fiber optic cables. ADA handicap ramps will be rebuilt to meet standards. This project involves the rebuilding of traffic signals at the following six intersections:

  • David Road and Marshall Road
  • David Road and Bigger Road
  • David Road and Wilmington Pike
  • Ackerman Blvd and E. Dorothy Lane
  • Marshall Road and Wilmington Pike
  • Patterson Road and Rembrandt Blvd

Bid Results 

Bid Tab

Contractor

Capital Electric

Project Engineer

Irina Titova-Spang, PE, PTOE