Sidewalk, Curb and Drive Approach Repair

Status Update:

October 12, 2017:  Milling and paving of the roads will begin October 17th. Work should be completed by October 27th, depending on the weather. Pavement markings will then be placed on Braddock Street. Please obey No Parking signs when posted. We appreciate your patience and cooperation as we complete this project.

September 19, 2017: Concrete work is almost complete for this project. Paving is expected to begin in early October.

August 24, 2017: Concrete work is completed on Alvarado, Baylor, Braddock and Tiffany. The contractor is currently performing concrete work on Delaney. Paving is expected to begin in mid-September.

Curb ramps are being replaced on East David Road from Hastings Drive to Renwood Drive.

August 11, 2017:  The contractor is completing the second sides of Alvarado, Baylor, Tiffany and Braddock—Hackney to Stroop.  Work will soon begin with full curb replacement on the east side of Braddock from Hackney to Olsen.  The contractor will begin work on Delaney in approximately 2 weeks.

 

 

August 4, 2017:  One side of  Alvarado, Baylor, Braddock and Tiffany have been completed.  The contractor will begin work on the west Delaney and continue with the other sides of the above streets next week.

July 18, 2017:  The contractor has begun.

July 12, 2017:  Concrete sawing will begin the last week of July.

June 19, 2017:  Construction is expected to begin in late July.

Project Description:
This project includes repair of deteriorated concrete curbs, drive approaches and sidewalks.  Property owners are responsible for the necessary repairs of the curbs, drive approaches and sidewalks and be assessed the cost for the repairs.  After the concrete work has been completed, the road will be repaved at a future time.  Click below to view informational letter sent to residents.
Info Letter Sent to Residents
 Project Limits:  
The project will include improvements on Alvarado Street, Baylor Court, Braddock Street, Delaney Street and Tiffany Drive.  Click below to view a map of streets included in this year’s program.
Map of Streets to be Repaired
Contractor:
America’s Decorative Concrete
1857 ST RT 571 W
Greenville, OH 45331
Bid Results:
2017 Sidewalk Repair Bid Results
2017 Sidewalk Repair Bid Tab
Project Engineer:  Diane Wuensch, P.E.
Email:  Diane.Wuensch@ketteringoh.org

 

Close window