Sidewalk, Curb and Drive Approach Repair – 2019 Project

Status Update:

October 9, 2019: The concrete work in the Wenzler Park area is almost complete. The contractor will then move to the outlying areas to complete concrete work at miscellaneous locations. Milling of the streets in the Wenzler Park area has started. Paving is anticipated to begin on October 10th. Anticipate project completion by November 2nd.

September 18, 2019: The contractor is continuing with concrete work on Benfield Drive and will begin on Kenosha Road the week of September 23rd. Outlying properties (not in the Wenzler Park neighborhood) will be completed last.

Expected project completion is November 2, 2019.

August 27, 2019: The contractor has started concrete repairs on the north side of Benfield Drive beginning at Sharewood Court and is heading eastward.

August 15, 2019: Adleta Construction has begun to saw cut areas that are marked on Benfield Drive.

July 29, 2019: Adleta Construction expects to begin work in early August.

June 18, 2019: A pre-construction meeting with Adleta Construction is scheduled for today.

Bid Date: February 21, 2019

Project Description:
This project includes concrete repair of deteriorated curbs, sidewalks and drive approaches.  Property owners will be responsible for the necessary repairs to the curbs, sidewalks, and drive approaches and will be assessed the cost for the repairs.  After the concrete work has been completed, the roads will be milled and repaved.

Informational Letter to Residents

 

Project Limits: 
The project will include improvements on Ascot Court, Benfield Drive, Bentwood Court, Kenosha Road, Sinton Place, Stoneview Court, Twinbrook Lane, and Oakmont Avenue (from Benfield Drive to Lincoln Park Boulevard). These streets are highlighted in orange on the map below.

Map of Wenzler Neighborhood Construction Projects 

 

Bid Results

Bid Tab

Contractor: Adleta Construction

Project Engineer: Diane Wuensch, P.E.
Email:  Diane.Wuensch@ketteringoh.org

 

Close window