Leaf Collection Update: Crews are currently working in District 5 and are progressing forward through the districts.  Districts are picked up in numerical order, so please have your leaves raked and placed by the curb before we get to your area. Please check the map for your leaf district.

Sidewalk, Curb and Drive Approach Repair – 2018 Project

Status Update:

October 4, 2018: The contractor is working on the north side of Cushing as well as the handicap ramps on Far Hills.

September 27, 2018: The contractor is currently working on the south side of Rockhill Avenue and expects to move to the north side of Cushing Avenue next week, weather permitting

September 21, 2018: Concrete work continues on Rockhill and Cushing.

September 17, 2018: The contractor will be working on Rockhill and Cushing this week.  Parking may be limited to one-side of the street during construction.

September 11, 2018: The south side of Cushing Ave is complete.

August 24, 2018:

Rockhill/Cushing/Lewiston area: Weather permitting, the contractor will complete work on the south side of Cushing Ave by Tuesday, August 28th and then move over to the south side of Rockhill Avenue. They will distribute door hangers to properties where they will be working in front of the driveway. Parking may be limited to one-side of the street during construction.

August 17, 2018:

Rockhill/Cushing/Lewiston area: The contractor is working on the south side of Cushing Ave working west to east. They will distribute door hangers to properties where they will be working in front of the driveway. Parking may be limited to one-side of the street at a time during construction.

August 1, 2018:

Bromfield area: Concrete repairs and paving at complete. Manhole adjustments still need completed.

Rockhill/Cushing/Lewiston area:  The contractor will be in the area for concrete repairs in August.

July 17, 2018:

Bromfield area: Paving will begin on Thursday July 19th and is could last up to a week, depending on the weather.

Rockhill/Cushing/Lewiston area:  The contractor will be in the area for concrete repairs in August.

July 3, 2018:

Bromfield area: Concrete work and yard restoration are completed. Montgomery County Environmental Services will be repairing sanitary manholes before we replace the asphalt. Paving may start as early as the week of July 16.

Rockhill/Cushing/Lewiston area:  Saw cutting of concrete has started on Rockhill. The contractor will be in the area doing concrete repairs towards the end of July.

June 18, 2018:  We expect the concrete work in the Bromfield area to be completed by approximately June 25th, weather permitting.  Saw cutting on the south side of Rockhill will begin on June 19, 2018. No Parking signs have been posted.

June 8, 2018: Construction has started in the North and South Bromfield neighborhood and will continue to the Rockhill, Cushing, Lewiston neighborhood. They will distribute door hangers when they are going to be in front of your house. Parking may be limited to one-side of the street at a time during construction.

May 22, 2018: The contractor will begin saw-cutting concrete the week of May 29th, beginning in the North and South Bromfield neighborhood and continuing to the Rockhill, Cushing, Lewiston neighborhood. They will distribute door hangers. Parking may be limited to one-side of the street at a time during construction.

May 3, 2018 : Construction Letter to Residents 5-3-18

April 5, 2018:  Work is schedule to begin the end of April starting on North and South Bromfield Road.

Bid Date:  March 1, 2018.

Project Description:
This project includes concrete repair of deteriorated curbs, sidewalks and drive approaches.  Property owners will be responsible for the necessary repairs to the curbs, sidewalks, and drive approaches and will be assessed the cost for the repairs.  After the concrete work has been completed, the road will be milled and repaved. Click below to view informational letter sent to residents.

 05-118 Info Letter OCT 2017
 Project Limits:  
The project will include improvements on Lewiston Road, Cushing Avenue, Rockhill Avenue, Delaine Avenue, North Bromfield Road, South Bromfield Road, and Storms Road.  Click below to view a map of streets included in this year’s program.
Map of project area – Revised 3-6-18
Contractor:

L.J. DeWeese Co., Inc.
3616 Tipp-Cowlesville Road
Tipp City, OH 45371
937-440-1736

Bid Results
Bid Tab
Project Engineer:  Diane Wuensch, P.E.
Email:  Diane.Wuensch@ketteringoh.org

 

Close window