The City of Kettering partners with Wright State University every two years to conduct a Kettering Resident Satisfaction Survey.  Emails with a link to the online survey went out yesterday from Carol Murray, our partner at Wright State, to a randomly selected group of Kettering residents.  If you received an email it is a valid survey and we appreciate you taking the time to provide your feedback.

Oak Creek Improvements – Phase II

Status Update:

October 27, 2017: Project is complete except for minor punch list items. Thank you for your cooperation during this project.

October 12, 2017:  Milling and paving of the roads will begin October 16th. Work should be completed by October 27th, depending on the weather. Please obey No Parking signs when posted. We appreciate your patience and cooperation as we complete this project.

September 19, 2017:  The concrete work has been completed on all streets. The contractor will be repaving the streets in early October.

August 24, 2017:  The concrete work has been completed on one side of each street in the project.  Concrete work on Colony Way is completed.  The contractor is completing concrete work on the second side of Sugar Maple Drive, and will then continue with the second sides of Oakbrooke Drive, Acme Court, Bliss Place, Berrycreek Drive and Oakvista Place.

Pavement repairs and repaving of the roads will begin after all concrete work is completed.

Anticipated completion is mid to late October.

August 11, 2017: The contractor is continuing work on one side of Oakbrooke Drive, Acme Court and Bliss Place and then will move to Berrycreek Drive and Oakvista Place.  After completing one side of all streets, the contractor will begin work on the opposite sides of each street.  Pavement repairs and repaving of the roads will begin after all concrete work is completed.

August 4, 2017:  The contractor has completed one side of Sugar Maple and Colony Way.  They are currently working on east side  Oakbrooke.

July 12, 2017: Concrete saw-cutting is underway.  Concrete repairs will begin in the next few weeks.

May 18, 2017: Construction is now expected to begin in August 2017.

April 7, 2017:  Construction is expected to begin in May 2017.

January 27, 2017:  Preliminary assessment letters mailed to residents.
December 1, 2016:  Preliminary measurements are underway to prepare for a spring bid.

Project Description:
This project includes concrete repair of deteriorated curbs, sidewalks and drive approaches.  Property owners will be responsible for the necessary repairs to the curbs, sidewalks, and drive approaches and will be assessed for the repairs.  After the concrete work has been completed, the road will be milled and replaced.

Project Limits: 
The project will include improvements on Sugar Maple Drive, Colony Way, Acme Court, Bliss Place, Oakbrooke Drive, Ivyton Court, Berrycreek Drive and Oakvista Place.  Click below to view a map of the streets included in this year’s program.

Map of Streets to be Repaired
Info Letter to Residents

Contractor:
R.A. Miller Construction Co.

4148 Augspurger Road

Hamilton, OH 45001

Bid Results:

2017 Oak Creek Phase II Bid Results

2017 Oak Creek Phase II Bid Tab

Project Engineer:  Diane Wuensch, P.E.
Email:  Diane.Wuensch@ketteringoh.org

 

Close window