Leaf Collection Update: Crews are currently working in District 5 and are progressing forward through the districts.  Districts are picked up in numerical order, so please have your leaves raked and placed by the curb before we get to your area. Please check the map for your leaf district.

Oak Creek Improvements – Phase III

Status Update:  

October 18, 2018: This project is now complete.

October 10, 2018: Paving is now complete. Miscellaneous work items will be performed soon.

October 4, 2018: The milling is now complete, paving continues.

September 27, 2018: Milling of the old pavement has begun; it is expected to take 5 -7 days.  Paving will follow shortly thereafter.

September 21, 2018: Concrete work continues on Oak Valley Drive.

September 11, 2018: Concrete work will continue throughout the plat, the project is expected to be paved in October.

August 1, 2018: Concrete work continues throughout the neighborhood.

July 17, 2018: The contractor continues to progress through the plat.
July 3, 2018:  The work continues.
June 18, 2018:  The contractor is actively working in the neighborhood replacing sidewalk, drive approaches and curbs.
May 17, 2018:  Saw cutting areas to be replaced has begun.  Concrete replacement work will begin in early June.

Bid date: February 22, 2018

Project Description:
This project includes concrete repair of deteriorated curbs, sidewalks and drive approaches.  Property owners will be responsible for the necessary repairs to the curbs, sidewalks, and drive approaches and will be assessed the cost for the repairs.  After the concrete work has been completed, the road will be milled and repaved.

Project Limits: 

Map of Streets to be Repaired
Oak Creek Info Letter

Contractor:

RA Miller
4148 Augspurger Rd Hamilton OH 45011
513-896-5011

Bid Results

Bid  Tab

Project Engineer:  Chad Ingle, P.E.
Email:  Chad.ingle@ketteringoh.org

 

Close window