Hilton Drive Improvements

Status Update: 

April 1, 2019: A pre-construction meeting is scheduled for April 12th.  Work is anticipated to start in May.

March 12, 2019: The project is anticipated to start in May. The construction work will require a detour for all through traffic. Only residents that live within the construction limits (Cardington Road to Patterson Boulevard) will be permitted to access Hilton Drive. Signs will be placed for the detour route. Please see attached DETOUR MAP. Work is expected to be complete in late fall, 2019. Access will remain open for the Hills and Dales MetroPark White Oak Camp entrance off of Glenbeck Avenue.

Detour Plan

Bid Date: This project is scheduled to bid on February 28, 2019

Project Description:
The project includes infrastructure replacement of gas mains by Vectren, water main by Montgomery County Engineering and roadway work by the City of Kettering.   Resurfacing of Hilton Drive  from Cardington to Stockton. This includes the removal and replacement of the asphalt surface, as well as related items (pavement markings, traffic detection, etc). The project also includes the removal and replacement of deteriorated curbs and drive approaches.

Project Location: Hilton from Cardington to Patterson

Bid Results

Bid Tab

Contractor: R.B. Jergens Construction Co.

Project Engineer: Chad Ingle,  P.E., P.S.
Email: Chad.Ingle@ketteringoh.org

Hilton neighborhood meeting presentation 11-28-18

 