ODOT SR-48 (Far Hills Avenue) Resurfacing – Dorothy Lane to David Road

Status Update: July 23, 2021: Thank you for your patience – paving is complete! The remaining work is expected to take several weeks: adjusting castings to grade, plus installing pavement markings and in-pavement reflectors. Completion is anticipated in July.
Occasional congestion should be expected when remaining work is performed. Please contact John Sliemers, Assistant City Engineer, with questions at 937-296-2436.

Project Description: The project, managed by the Ohio Department of Transportation (ODOT), includes resurfacing of the asphalt surface.

Project Location: Far Hills Avenue from north of Dorothy Lane through David Road.

Traffic Location: Two-way traffic will be maintained. Construction will occur during daylight hours.

Project Engineer: John Sliemers,  P.E.
Email: John.sliemers@ketteringoh.org 

Contractor: Barrett Paving Materials, Inc