East David Road Resurfacing-Ackerman Blvd to Wilmington Pike

Status Update:

October 17, 2019: This project is now complete.

September 26, 2019: The paving is now complete. The contractor is currently working on pavement striping and utility manhole adjustments . After this is done, the project will be complete.

September 6, 2019: The contractor will begin milling David Road from Marshall Road to Wilmington Pike starting on September 10th. The milling is expected to take 4-5 days. After the milling is complete, the contractor will place the new asphalt surface which is expected to take 5-6 days. Finally, utility manholes will be adjusted and the pavement striping will be completed.

August 15, 2019: The concrete work, east of Marshall, is expected to be completed by the end of August. The contractor will then schedule to pave the eastern half of the project in the month of September.

August 1, 2019: Starting the week of August 5, the contractor will be milling off the old surface and paving the section of David Road from Marshall Road to Ackerman Blvd. Traffic will be reduced to one lane of traffic in each direction. Concrete work will continue on the east bound lanes from Marshall Road to Wilmington Pike.

July 29, 2019: Concrete work is ongoing in the east bound lanes and median.

July 10, 2019: Concrete work continues in the west bound lane.

June 18, 2019: Concrete work is underway in the west bound curb lane.

May 30, 2019: The contractor will begin saw cutting the existing concrete curbs for replacement the week of June 3th. This work will require a single lane closure.

May 1, 2019: The contractor is anticipating getting started the first week of June and will begin with concrete work on the western section (between Marshall Road and Ackerman Blvd).  After the concrete work is complete, they will mill and pave the road.

March 22, 2019: This project is expected to begin in June 2019.

March 12, 2019: The project will be completed in two phases, starting in spring with the work between Wilmington Pike and Marshall Road. Phase one will include the removal and replacement of curbs and drive approaches. Phase 2 will start once school is out and will include the removal and replacement of curbs and drive approaches in the section between Marshall Road and Ackerman Boulevard. The contractor will complete the project with the final removal of the asphalt surface and paving.

Bid Date:  February 14, 2019.

Project Description:
The project includes resurfacing of East David  Road from Ackerman Blvd to Wilmington Pike. This includes the removal and replacement of the asphalt surface, as well as related items (pavement markings, traffic detection, etc). The project also includes the removal and replacement of deteriorated curbs and drive approaches.

Project Location: East David Road from Ackerman Blvd to Wilmington Pike

Bid Results Bid Tab


Contractor: Barrett Paving Inc.

Project Engineer: Chad Ingle,  P.E., P.S.
Email: Chad.Ingle@ketteringoh.org

Close window