Bigger Road Resurfacing

Status Update:

August 2, 2018: Traffic is restricted to one lane southbound as curb repair continues in the southbound, curb lane.

The concrete work on Bigger Road is anticipated to be complete by the middle of August. Once it is complete, the contractor will schedule the milling off of the old asphalt and placing new asphalt.

July 3, 2018:  The contractor has begun saw cutting on Bigger Road. This phase will take approximately two weeks.

May 17, 2018:  Work is scheduled to begin in July.

Project Description:
The project includes resurfacing of Bigger Road from David Road to the southern corporation limit with Centerville. This includes the removal and replacement of the asphalt surface, as well as related items (pavement markings, traffic detection, etc). The project also includes the removal and replacement of deteriorated curbs and drive approaches.

Project Location:
David Road to the Centerville Corp. line
 
Contractor:
John R. Jurgensen Construction
1780 Enon Rd.
Springfield, OH 45502
Bid Results
Bid Tab

Project Engineer: Chad Ingle,  P.E., P.S.
Email: Chad.Ingle@ketteringoh.org

Close window