Bigger Road Bridge Railing Repair
Status Update:
April 15, 2020: All the punch list items have been addressed and railing repair is complete.
April 6, 2020: Railing has been installed, only minor punch list items remain.
March 23, 2020: Installation of the railing will take place this week.
January 29, 2020 The wall is now complete. The railing is being fabricated and should be ready for installation by mid-February.
Project Description: The bridge railing on northbound Bigger Road near 4530 Bigger Road was struck by a car and is in need of repair. The repairs will begin Wednesday January 15, 2020 and last approximately one week, depending on the weather.
Traffic Impact: The northbound curb lane of Bigger Road, from 4540 Bigger Road to near David Road will be closed beginning Wednesday January 15, 2020 through Friday January 17, 2020. The intersection of northbound Bigger Road at David Road will remain open. Further closures may be needed during the week of January 20-24th.
Project Engineer: Mike Zink
Email: mike.zink@ketteringoh.org