Asphalt Overlay 2019

Status Update: 

April 16, 2019: Milling is taking place on Forrer Blvd. as well as Donson Drive.  The milling contractor will then move to Rahn Road beginning at Wilmington Pike heading to the west.

April 1, 2019: Work has started on the replacement of the curb ramps. The contractor is expecting to start the full depth repairs on Robert Dickey Parkway and Brooklands Road the week of May 13th. They are also planning to start the milling and overlay of the streets on May 13th. Click the link below for a list and map of street included in this year’s project.

March 22, 2019: Concrete work is expected to begin the week of March 25th.

March 12, 2019: The project is anticipated to start work in April on the replacement of concrete curb ramps to make them ADA accessible on the streets that will be paved. Once this work is complete, the contractor will schedule the paving process. The paving process is anticipated to continue through the summer.

Bid Date: February 7, 2019

Project Description:
Each year the City of Kettering evaluates the conditions of all the city streets to create the annual street maintenance program.  After the streets are evaluated, they are then ranked according to the pavement condition and a list is created for the streets that may be paved this year.

Project Location:
This year’s Asphalt Overlay Program includes milling the existing asphalt and paving new asphalt on several residential streets.

List of Streets to be Paved in 2019

Map of Streets to be paved in 2019

Bid Results Bid Tab

Contractor: Barrett Paving Inc.

Project Engineer: Chad Ingle,  P.E., P.S.